Update on Goodman South Campus

//Update on Goodman South Campus

Update on Goodman South Campus

South Campus Construction
South Campus Construction
South Campus Construction
South Campus Construction

If you’ve driven by the Goodman South Campus site lately you’ve seen that construction is progressing and we are on track to open on September 3, 2019. To call this a momentous occasion is to understate the transformative impact this campus will have on the students it will serve, the residents of our 12-county district, employers who benefit from the economic vitality created and sustained by a steady stream of highly trained workers in southcentral Wisconsin, and for the communities of which we are a part. This full-service college campus is in a long-underserved neighborhood, moving the conversation from bold vision to becoming a promise kept.

The campus will have a projected enrollment just over 1,500 students for fall 2019. At full capacity 5,000 students will study in the classrooms. In addition to a broad range of academic options offered at the Goodman South Campus, students will have access to classes at Truax through a regular shuttle bus.

ALL are invited to a Grand Opening Celebration on Saturday, September 28 from Noon to 4 p.m. with a formal program to begin at 1 p.m. Goodman South Campus is located at 2429 Perry Street, Madison.

Many in our community contributed to make this campus a reality. Thank you!! If you are interested in supporting the Goodman South Campus Building or contributing to scholarships, you can donate online.

Construction update and live-stream:
Projects currently underway on the 75,000-square-foot campus include:

  • Drywall finishing is complete and painting has begun on second floor.
  • MEP trades are doing finish work throughout the building.
  • Building finishes are ongoing throughout the building.
  • Curtain wall work is nearly complete on area B. A few pressure plates still need to
  • be installed.
  • Resilient flooring is being installed on the first and second floors.
  • Work is on going on the parking lots. Curbs and remaining sidewalks will begin next week.
  • Doors and hardware are being installed on the lower level.
  • Foundations have been poured for the large planters at the north entry.
  • Lab casework installation is on-going in the lower level.
  • The first load of classroom furniture is scheduled for delivery on 6-19-19 for the lower level.
  • Miron’s overall project completion schedule shows August 25, 2019 as the substantial completion date.

When completed, the campus will feature a brightly lit Café Servery and seating area, a library, a Student Achievement Center, flexible classrooms, a practical nursing lab, a chemistry lab and main service counter. The South Courtyard Entrance will feature a landscaped seating area, bicycle parking and vehicle parking. Two live webcams are recording the construction. (Camera 1: https://app.truelook.com/?u=mm1526503625 | Camera 2: https://app.truelook.com/?u=mm1526503760)